CIA engagement planning case: build a defensible work program
For a supplier-bank-change audit, start from changes that actually became active and trace each to independent approval before activation. Testing only completed approval forms misses changes with no form. The worked plan below connects the diverted-payment risk to scope, criterion, population, and the evidence needed to answer the objective.
Need the concepts first? The engagement-planning method.
Worked plan: supplier-bank changes after a system migration
| Decision | How to apply it | Mistake to avoid |
|---|---|---|
| Risk and objective | Risk: payments diverted through unauthorized bank changes. Objective: determine whether changes were independently approved before use. | Testing payment totals without examining authorization of the bank changes. |
| Scope | Cover the new system’s supplier-bank changes during the stated post-migration quarter, including privileged-user activity. | Assuming the old paper process covers changes made directly in the new system. |
| Criterion | Apply the authorized policy requiring independent approval before activation; establish suitable criteria if policy is inadequate. | Using a deadline chosen after reviewing the exception count. |
| Population and procedure | Reconcile the activation log, select changes for the objective, and compare approval identity and timestamps with activation. | Starting only from approved requests, which omits unauthorized changes. |
| Resources and limits | Obtain access-log expertise and reliable extracts. Address missing logs before claiming coverage of the period. | Keeping the original conclusion scope after removing an essential test. |
Risk and objective
Risk: payments diverted through unauthorized bank changes. Objective: determine whether changes were independently approved before use.
Avoid: Testing payment totals without examining authorization of the bank changes.
Scope
Cover the new system’s supplier-bank changes during the stated post-migration quarter, including privileged-user activity.
Avoid: Assuming the old paper process covers changes made directly in the new system.
Criterion
Apply the authorized policy requiring independent approval before activation; establish suitable criteria if policy is inadequate.
Avoid: Using a deadline chosen after reviewing the exception count.
Population and procedure
Reconcile the activation log, select changes for the objective, and compare approval identity and timestamps with activation.
Avoid: Starting only from approved requests, which omits unauthorized changes.
Resources and limits
Obtain access-log expertise and reliable extracts. Address missing logs before claiming coverage of the period.
Avoid: Keeping the original conclusion scope after removing an essential test.
A decision path you can use
- 1Define the diverted-payment exposure
- 2Build the risk-to-evidence chain
- 3Resolve resource and access gaps before approval
Understand the method
Work through the reasoning
Understand what the migration changed
Begin the supplier-bank-change case by learning how a change reaches the live supplier record. Identify the request channel, verification step, approver, activation mechanism, and first payment. Compare the new process with the old one. A migration may preserve the written policy while introducing administrator privileges or interfaces that bypass its normal workflow.
Use that understanding to formulate the risk assessment. The important exposure is payment diversion through an unauthorized instruction, not simply missing paperwork. Ask whether the system prevents activation before approval, whether approval is genuinely independent, and whether urgent changes follow another route. Document assumptions that need confirmation rather than treating the process owner’s walkthrough as proof of operation.
Build procedures that can find the failure
An objective-linked work program starts from the event whose authorization matters: activation of the new bank details. Obtain the relevant change population, assess completeness, and connect each selected event to the required evidence. Starting with signed requests answers a different question because changes with no request cannot enter that selection.
Specify what the auditor will compare. Approval identity addresses authority and independence; timestamps address sequence; verification records address authenticity of the instruction. A procedure that says only “check approval” leaves these distinctions unresolved. Explain how exceptions, missing records, and conflicting timestamps will be investigated so the test can produce a supported conclusion.
Connect coverage, skills, and evidence availability
The quarter after migration may contain different configurations, emergency access, or data conversion issues. Establish which periods and pathways the work covers. Consider whether a system specialist is needed to interpret logs or whether business records can corroborate them. A familiar spreadsheet extract is not automatically the complete population of activated changes.
Estimate the work needed for ordinary items and likely exceptions, including review and communication. If essential logs have expired, identify alternative evidence and assess the resulting limitation. Reducing the number of procedures while retaining the same broad assurance claim is not a resource solution. Resolve the relationship between scope, effort, and the conclusion before the work program is approved.
Revise the plan when fieldwork changes the risk picture
Suppose testing reveals a service account that changes bank details without creating the normal approval event. That discovery challenges the population and the original control understanding. Determine which transactions used the account, whether complementary controls exist, and how much of the period is affected. The finding may require changes to both procedures and scope.
Record why the change is necessary, obtain the appropriate approval, and communicate its effect on timing and coverage. Preserve the original planning rationale so a reviewer can understand how the engagement developed. A defensible plan is adaptable, but changes should be governed by evidence and objectives rather than a desire to avoid inconvenient results.
Original teaching example
Apply the method to a decision
The scenario
A purchasing audit begins after a system migration. The team proposes selecting 25 signed approval forms because those are easy to retrieve. Some supplier changes can be activated directly without a form.
The decision
Start with a reconciled population of activated changes and trace back to approval evidence, including cases where that evidence is missing.
The proposed form-based population selects for documented approval and may exclude the failure the audit is looking for. Verify log completeness, identify relevant changes, and inspect approval identity and timing. The number 25 alone says nothing about sufficiency; the selection must fit the objective and intended inference.
Independent hypothetical case. It is not an official IIA question, an actual investigation, or a scoring prediction.
A second application
The exception reveals an unplanned interface
The situation
A bank change appears in the live supplier table but not in the workflow export. IT explains that an overnight interface can also update bank details.
Reason through it
The original export does not cover the complete activation population. Audit needs to understand the interface, reconcile its changes, and evaluate its authorization controls before using workflow results to describe the entire process.
Take the decision
Amend the population and work program through the approval process. Report the limits of any coverage that cannot be recovered.
Original hypothetical teaching case.
Check your understanding
Choose the best answer, then check the reasoning for each alternative. These short learning checks are not a full exam simulation. Answers are not saved or sent.
Questions about this topic
Can an engagement plan change during fieldwork?
Yes. New risks, evidence, or access restrictions can justify changes. Document the rationale, obtain the appropriate approval, and communicate the effect on scope, resources, and conclusions.
Why does the direction of testing matter in this planning case?
Tracing from activated changes to approvals can reveal changes without authorization. Selecting only existing approval forms excludes that failure from the starting population. Choose the direction that can expose the risk named in the objective.
Sources and syllabus scope
Prepared by MiloPrep editorial team. Source links checked 2026-10-10. These notes and cases are independent teaching material; the IIA sources do not verify or endorse them.
- IIA expanded syllabus
Establishes the examined topics. Primary domain: Engagement Planning (50% of Part 2). This is a domain allocation, not a separate weight for this lesson.
- Global Internal Audit Standards reference
- Locator: Standards 13.1-13.6. Supports the professional requirements cited here; our scenarios and solution steps are original applications. Current IIA Standards resources.